Perimeter Bird Netting

Large-Scale Perimeter Bird Netting – Distribution Centre

Site Type

Distribution centre – mezzanine perimeter and cold room roof

Scope

314.1m of perimeter netting, around half of it 12.5m high, plus a 104m floor-to-ceiling run along the security fencing line

Access

Rope access, MEWP and vertical mast lift, allocated run by run

Completed

Location

Lancashire

Technician working from a MEWP at roof height inside a large distribution centre

We were appointed to supply and install 19mm bird-exclusion netting at a large distribution centre, as a single lump-sum package: 314.1 linear metres of perimeter netting, around half of it 12.5m high, plus a 104m floor-to-ceiling run along the security fencing line.

At this scale, bird exclusion is as much about access and coordination as it is about netting.

Netting being fixed to structural steelwork from a work platform

The challenge

  • Height and variety of access. Around half of the netting is 12.5m high, fixed from the mezzanine up to the roof structure and from the cold room roof, so no single access method suited every location.
  • Working around the operation. Exclusion zones and traffic control below the work, with escape routes, sprinklers, detection and lighting kept clear.
  • A change of route before start. Services installed since the survey blocked part of the planned route.
Netting dropped the full height from the roof steelwork to the mezzanine edge

Our approach

  • Access matched to each run. Our IRATA Level 3 supervisor chose rope access (around 30–35% of the installation), a MEWP or a vertical mast lift for each area.
  • Specification. 19mm black No-Flame netting, fixed to a perimeter wire with crimped ferrules.
  • Controlled work areas. Barriers and signage below the work, lanyarded tools, services checked before drilling, and areas checked for birds and nests before enclosing.
  • Rescue and supervision. A planned rescue arrangement with kit on site, daily briefings and stop-work authority for everyone on the job.

Adapting the route

We issued a route variation before starting on site. The netting now runs beneath the mezzanine down to the office ceiling, the staircase is fully enclosed so birds cannot pass through, and a cap net was added, with no change to programme duration or cost.

Before and after

BEFORE Mezzanine edge and roof steelwork before netting
AFTER Mezzanine edge and roof steelwork after netting, with the net dropped to the mezzanine edge

The result

We started on site on 1 October and completed on 15 October 2026, five days ahead of the 20 October deadline. There were no incidents, the job was delivered on budget, and all paperwork was completed and handed over.

The project shows what a large installation takes: access matched to each run, work planned around an operational building, and a route change absorbed without affecting programme or cost.


Get In Touch

Give us a call on 0191 447 1788 or send an email to hello@tyneropeaccess.com to tell us about your job.

Want to see more real jobs like this one?

We add new case studies as we complete them - join the list to see them first.